June 2021 Customer Update

July 9, 2021

We are excited to share with you a second quarter update on your . Construction and infrastructure are progressing rapidly whilst Eynesbury is growing into a thriving community.

In Stages 8A, 8B and 8C our civil contractors have fully completed sewer, stormwater drainage and water pipeline work.

Road construction is well underway with kerbs installed and some road pavements asphalted. With civil works, we are 80% along the construction timeline and expect all works to be completed on time.

In Stages 6A, 6B and 6C civil construction has commenced on site with bulk earthworks completed. Work on sewer and stormwater drainage is currently underway.

Construction has also commenced on Stages 6D, 6E and 6F.