December Customer Update

December 17, 2020

We are pleased to provide you with our last project update for Eynesbury for 2020. We take this opportunity to wish you and your family our best wishes for Christmas and the Festive Season.

It has been a big year at Eynesbury with Stage 4 and Stage 11 titles being registered. Stage 5A & 5B are now complete, authority compliances have been achieved and the titles are anticipated to be registered early 2021 in January.

In Stage 8A, 8B & 8C, civil construction works are well underway with bulk earthworks nearly complete and drainage works are well underway.